An award does not make neighboring land eligible
The Maryland Public Service Commission conditionally selected the 40-megawatt Jade Meadow III Battery Storage Project in Barton on October 1, 2026. It describes a combined solar-and-storage facility on reclaimed coal-mine land. The project still needs to apply for construction approval.
That selection concerns a particular proposal. It does not establish a countywide lease program, available electrical capacity or demand for neighboring acreage. If someone uses the award to explain an offer, ask what relationship the offer has to the selected project. A separate site needs its own work.
Reference: Maryland PSC: October 1, 2026 conditional transmission-storage awards

Check where zoning actually applies
Garrett County says it has no countywide zoning. Its zoning page identifies town and Deep Creek Watershed zoning areas and directs owners to the county map’s zoning layer. It also notes that building permits may be required outside zoned areas.
Find the parcel on the map and ask the responsible office which requirements apply to this design. An unzoned location should not be treated as permission to install a battery. Ask the project team to explain state construction review and any building, electrical, grading, access or other approvals it expects to need.
Reference: Garrett County: where zoning applies and how to check the map
Reclaimed land needs its own investigation
If your land was mined or filled, share what you know about its history. Useful records may include reclamation plans, previous studies, restrictions or information about work already done. Do not guess at conditions beneath the surface if you do not know them.
Ask who would investigate ground conditions and drainage, who pays for that work and how access for testing would be arranged. Identify areas you do not want disturbed. A broad flat area can be worth examining, but appearance alone cannot establish whether it can support the proposed equipment or construction traffic.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landExisting solar changes the questions to ask
Maryland DNR’s April 2026 archive identifies a final November 2025 CPCN for Jade Meadow III’s 300-megawatt solar project. That solar record is distinct from the October 2026 conditional battery award and its separate construction-review requirement. Ask which decision covers the actual equipment and land rights being proposed.
For land with solar rights already granted, read those agreements before discussing another option. Ask whether someone already controls storage, electrical routes, access or expansion areas. Make sure the proposed battery footprint and supporting equipment are compared with the land already committed.
Ask whether storage would use an existing electrical agreement or require a separate one, and who has verified that arrangement. A solar project’s approval or connection should not be assumed to cover a battery of any size. If several companies are involved, have them explain which one would contract with you and operate the equipment.
Reference: Maryland DNR: April 2026 archived project approval summary · Maryland PSC: October 1, 2026 conditional transmission-storage awards
Check the area and equipment covered by each filing
Jade Meadow III’s May 20, 2026 solar progress report gave an October 1, 2026 expected start for site development. An expected date in that report does not establish that work began. It also described equipment delivered to offsite storage, which is a different milestone from installing equipment on the property.
The August 26 filing submitted final grading plans for the northern portion of the solar project and said further areas would follow through permitting. A submitted plan is not proof of approval for every part of a combined project. These solar filings do not settle the battery construction review described in the October award announcement.
If work will happen in phases on your land, ask for a drawing identifying the equipment and area covered by each approval. Which land is needed now, which is reserved for later and which remains available for your use? Ask where construction vehicles and stored materials would go, including outside the first work area.
Compare that plan with the payment schedule. Would work on one area start rent for the whole reserved property or only part? Who can enter the later areas while they remain undeveloped? Have the agreement explain what is paid during the hold and when unused land is released.
Ask for dated progress notices that distinguish a plan submission, an approval, delivery, site work and operation. Find out who contacts you before the next area is disturbed and how a changed schedule affects gates, roads, drainage and the uses you retain.
Reference: Maryland PSC Case 9769: May 20, 2026 solar progress report, item 55, ML 330300 · Maryland PSC Case 9769: August 26, 2026 northern solar-area grading submission, item 56, ML 333640 · Maryland PSC: October 1, 2026 conditional transmission-storage awards
Include the road and retained land in the drawing
Request a plan that shows entrances, equipment, cables and temporary work areas. Identify roads you need for your own use, places where vehicles can turn and any route across someone else’s property. Ask what construction traffic is expected and how the proposed access would be maintained.
Consider how much usable property remains during construction and operation. Ask about screening, maintenance, noise assessment and emergency access for the actual design. The agreement should explain responsibility for removal and restoration, including roads or other improvements, rather than leaving those questions until the lease ends.
Start without commissioning a study yourself
Send Sunland your contact details and property location. Add Garrett County, the town or nearby road, current land use and any mining or solar history you know. Parcel numbers, acreage and supporting details are optional; you can say that a record is unavailable.
Explain what you want to learn and whether there is an offer or deadline already involved. You do not need an engineering report before making an inquiry. Further work must determine the site’s condition, rights, approval route, connection and commercial fit. An inquiry does not guarantee a project or commit you to lease or sell.
Questions landowners ask
Does no countywide zoning mean no approvals are needed?
No. Check the parcel’s zoning boundaries and the other approvals required for the proposed design.
Does reclaimed mine land automatically work for batteries?
No. Ground condition, access, rights and the electrical connection still need investigation.
What if a solar company already has rights to my land?
Mention that agreement. Storage and access rights need to be checked before a separate commitment.
Sources & further reading
Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.
- Maryland PSC: October 1, 2026 conditional transmission-storage awards
- Garrett County: where zoning applies and how to check the map
- Maryland DNR: April 2026 archived project approval summary
- Maryland PSC Case 9769: May 20, 2026 solar progress report, item 55, ML 330300
- Maryland PSC Case 9769: August 26, 2026 northern solar-area grading submission, item 56, ML 333640