A pilot project is context, not an offer for your land
In May 2021, Potomac Edison announced approval of two Maryland storage pilots: a reliability proposal in Allegany County and a battery paired with EV charging in Frederick County. That dated announcement describes particular projects and purposes.
It does not establish that the utility wants to lease your parcel today. If a developer mentions a nearby battery, ask what connection or commercial evidence relates to your site. Keep the existing project’s history separate from the proposed agreement in front of you.
Reference: Potomac Edison: historical May 2021 storage pilot announcement

Use the Maryland process for a Maryland parcel
FirstEnergy’s Maryland interconnection page provides Potomac Edison application resources and a separate wholesale interconnection link. Potomac Edison also operates outside Maryland, so a familiar company name is not enough to identify the applicable process.
Ask the developer which application route covers the proposed storage operation and why. A proposal to serve an existing customer is different from a proposal to sell electricity to the wider market. You can ask for that distinction without knowing the technical rules yourself.
Reference: Potomac Edison: Maryland interconnection resources
Understand a limited export proposal before relying on it
Potomac Edison’s February 2025 Maryland guidance describes site-specific limited export/import agreements that may avoid or reduce upgrades. Its engineering review determines the limit and revised grid impacts. The guidance calls for agreement before export and annual review; it does not approve a particular battery or promise that upgrades disappear.
Ask the developer to explain the proposed operation in plain language. When would the battery charge? How much could it send to the grid, and when? Is the company discussing a possible restriction or an agreement already accepted for the actual design? Request the document supporting the answer.
If the proposal is still being studied, ask what happens if the accepted limit is lower than expected. Could that change the equipment, connection route, project schedule or commercial offer? Have the company identify the decision it still needs before asking you to reserve land for a long period.
Keep the electrical limit separate from the physical land request. A restricted export amount does not by itself explain how many enclosures, access roads or cable routes the company wants. Compare the complete drawing with the proposed option or lease.
Reference: Potomac Edison: Maryland Limited Export Agreements, February 2025
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAsk who pays for studies, communications and changes
The published guidance mentions upfront study costs, a possible annual administrative fee and utility communications access. It says obtaining more capacity through a revised agreement requires a new interconnection application. These are questions for the project team, rather than tasks the landowner should assume it must perform.
Ask which company would hold the electrical agreement and pay the associated costs. If the proposal involves your business or a tenant’s account, have those responsibilities explained separately from rent. Request an account arrangement that your adviser can compare with the private land documents.
Find out how the company would manage the monitoring or communications equipment on the property. Where would it go, who would maintain it and what access would be needed? Include the relevant routes and facilities in the drawing instead of leaving them outside the described land area.
Discuss changes before signing. Could the company seek additional capacity later, add equipment or change the use of your electric service? Which changes require your consent and how would any extra land be paid for? The agreement should address the rights actually requested from you.
Reference: Potomac Edison: Maryland Limited Export Agreements, February 2025
Compare the utility drawings with the land agreement
Potomac Edison’s Maryland application page calls for a site plan and an electrical diagram identifying storage, metering and connection equipment. It also distinguishes engineering review from final review and authorization to operate. Ask the developer which stage it has reached.
Request a dated drawing showing the property boundary, entrance, battery equipment, transformer and cable route. Mark the uses you want to retain, including tenant access, deliveries and routes to other land. Ask where contractors would park and store materials during construction.
Have your adviser compare that drawing with the area and rights in the agreement. Is the company reserving the whole parcel or defined areas? Would an electrical-route change affect ground outside the fence? Ask how revised plans would be presented to you and whether they require an amended exhibit.
You can start a Sunland inquiry without preparing utility-grade drawings. Provide the location and what you know about the proposal. The company pursuing a connection should explain its application work; an initial property inquiry does not authorize the use of your electric account or a permit filing.
Reference: Potomac Edison: Maryland interconnection resources
A service-work request is a separate record
FirstEnergy’s Maryland interconnection page links a work-request tracker that now opens its construction and renovation resources. Those resources cover new, upgraded and temporary electric service. A work request for service should not be described to you as approval for a battery’s charging and export connection.
If the company shows you a tracking number, ask what work it covers and whose name is on the request. Is it construction power, a change to your existing business service or part of the final project connection? Request the separate interconnection reference and the utility’s response for the battery design.
Put the work requests beside the site drawing. Where would a temporary service enter, which equipment would remain afterward and would any trench or route cross land outside the proposed lease? Ask who pays for installation, ongoing charges and removal. Include a tenant if its service or access would be affected.
Keep account authority limited to the work you understand and approve. Ask whether you would become the customer responsible for charges or whether the project company holds its own account. Sending Sunland a property inquiry does not submit a utility work request or authorize a change to an account.
Reference: Potomac Edison: Maryland interconnection resources · FirstEnergy: new, upgraded and temporary electric service requests
Ask what remains after temporary electrical work
FirstEnergy’s service-help page says service-work timing can depend on customer steps, easements, storm restoration and materials. Its general lead-time chart is not a battery connection study or a promised construction date for your project.
If the developer needs longer to arrange service, compare the revised schedule with the option term and payment dates. Ask whether the extension is optional or automatic, what you receive during it and when the company must release land it no longer needs. A revised service forecast should not leave the reservation period unclear.
The same help page separates stopping an account from requesting removal of electric facilities. It describes a written removal request by an authorized person who can provide ownership paperwork. Ask the project company which facilities it would own, which the utility would own and who arranges their removal when the project ends.
Have the proposed restoration terms cover temporary poles, meters, cables, disturbed ground and remaining access rights as applicable to the actual plan. Who pays if utility removal takes longer than battery removal? How are retained facilities or routes agreed with you? Get the responsibilities and end condition stated before signing.
Reference: FirstEnergy: service-work timing and removal of electrical facilities
Find out whether the proposal depends on your business
If EV chargers or an operating business are part of the pitch, ask who owns each piece of equipment and which account supplies it. Would you be providing only land, or also taking on an operating role? Have those responsibilities described separately.
For an undeveloped parcel, say there is no existing service if that is the case. Do not use a neighboring meter as proof that the proposed charging and export arrangement can connect. Ask what new facilities and rights are being investigated.
Follow the route from the equipment to the connection
Ask for a sketch showing the battery area, access and proposed electrical route. Identify neighboring land, roads or existing easements the route would cross. A nearby substation may be relevant, but distance alone does not establish connection rights.
Tell the developer which field entrances, wooded areas or business access you want to preserve. If a route changes after studies, ask whether it would need your further agreement and how additional affected land would be paid for.
Tie a reserved period to understandable progress
Ask what the developer will investigate during an option and what updates you will receive. Find out what happens if a study requires costly upgrades, the connection point changes or the project stops. A pilot announcement should not replace these milestones.
Start an inquiry with the property location, utility if known and the part you could consider. Mention any previous proposal and records you have. Sunland can begin with that information; sending it does not reserve your land or guarantee a project.
Questions landowners ask
Does the 2021 announcement show land is being sought now?
No. It is historical evidence about specified pilots, not a current offer or parcel qualification.
Should I use Potomac Edison’s West Virginia resources for Maryland land?
Use the resources for the parcel’s state and proposed operation. Ask the developer to confirm the correct process.
Do I need an existing meter before contacting Sunland?
No. Explain whether the parcel has service and provide the location. Further research must establish the connection requirements.
Does a service-work tracking number prove the battery can operate?
No. Ask what work the request covers and obtain the separate connection approval for the actual battery design.
Sources & further reading
Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.
- Potomac Edison: historical May 2021 storage pilot announcement
- Potomac Edison: Maryland interconnection resources
- Potomac Edison: Maryland Limited Export Agreements, February 2025
- FirstEnergy: new, upgraded and temporary electric service requests
- FirstEnergy: service-work timing and removal of electrical facilities