Southern Maryland Electric Cooperative (SMECO) / Maryland

Battery storage land in SMECO’s service area

Ask how the battery would connect and whether a limit on exports changes the proposal for your land.

Could my land work?

Identify the utility serving the property and the proposed battery operation first. SMECO publishes connection resources, a solar hosting map and a limited-export policy. These are starting points for questions; they do not establish capacity or approval for a battery on your parcel. The project team should confirm the route for its actual design.

Confirm the service area and the proposed connection

SMECO describes its territory as Charles and St. Mary’s counties, most of Calvert County except the northern tip, and southern Prince George’s County. For a particular property, confirm service using the electric utility on the bill or ask about the location if the land has no service.

Tell the project team about any house, business or tenant already using electricity there. Ask whether the battery would use that existing service or a separate connection and account. A land lease offer should explain which arrangement the company intends.

Ask whether the proposal is standalone storage, storage paired with solar or equipment serving an existing customer. Also ask whether the connection is intended for the local distribution system or a transmission line. The developer should identify the applicable review process.

Reference: SMECO: service area

Model landscape illustration of battery storage sites and an electrical substation connected by roads and power lines.

Use SMECO’s resources for the questions they answer

SMECO’s solar and net-metering page links PowerClerk applications, connection standards and a solar hosting-capacity map. It notes that interconnection eligibility and net-metering eligibility can differ. Do not assume the solar program is the correct route for a separate battery facility.

Ask the developer what it has actually checked: the connection point, charging demand, exports and required studies. Request the date and status of any utility response. A screenshot from a solar map is not a complete answer to those questions.

The queue spreadsheet linked on that page is labeled updated December 31, 2019. It should not be treated as a current list of projects or available capacity. Ask for current project-specific information instead.

You do not need to complete an engineering application to make an initial land inquiry. A useful first discussion identifies the location, intended use and questions the project team must resolve before asking you for a longer commitment.

Reference: SMECO: interconnection resources and Limited Export Policy

Understand what limited export would mean

SMECO’s published policy lets customers with denied Level 2 or Level 4 applications request reconsideration using a proposed export-control and reporting scheme. Approval is subject to review, with possible field validation and recurring fees. It is not a general promise of approval.

If a developer mentions limited export, ask whether it has requested that review and received an actual response. Have it explain the proposed export limit, controls, monitoring and who pays the continuing costs.

Ask whether the battery can charge as planned too. An export restriction describes electricity leaving the project; the team still needs to explain the review of electricity drawn from the grid and any operational restrictions.

Discuss whether the revised operation changes the offer to you. Ask if rent, option timing or the company’s decision to proceed depends on a particular export allowance. Keep any agreed change in writing.

Reference: SMECO: interconnection resources and Limited Export Policy

QuestionRecord to request
What operation is proposed?Charging and export assumptions.
Has limited export been accepted?The actual utility response and conditions.
Who pays continuing costs?The company’s cost responsibility.
Does the land offer change?A written explanation or proposed amendment.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Keep your existing service and access clear

If you operate a business or rent buildings on the property, identify the service and access that must remain available. Ask whether construction would require an outage, moving equipment or changing an entrance. Discuss notice and responsibility for disruption before work begins.

Have the developer show equipment, cables, meters, roads and temporary work areas on one drawing. Mark existing utility rights and shared drives that you know about. The fenced battery area may not include every area needed for connection or maintenance.

Ask whether you will remain responsible for any account or charge associated with the project. If the proposal uses a separate account, clarify the responsible company and what happens when ownership changes. Do not let a drawing substitute for clear payment responsibilities.

Keep information about buried private lines, drainage and planned improvements with the property records. Explain any areas that cannot be disturbed so the team can address them before the agreement or layout is fixed.

Tie the land commitment to the unresolved work

Ask which connection decisions remain open and what the company expects to learn during the option term. Identify the payment, deadline and conditions for each extension. Compare the longest possible commitment with your own plans for the property.

If connection costs or operating limits change, ask when the company must tell you and whether it can continue holding the land. Have your adviser review the termination and release provisions rather than assume a utility decision ends the contract.

Public approval, electrical connection and private land rights answer different questions. Request a schedule identifying each step, the responsible company and the next point at which the proposal will be reviewed.

Before signing, discuss removal and restoration as well as construction. Ask who removes project equipment and repairs affected land if the proposal stops after preliminary work or when operation ends.

Send the location and what you would consider

Start with your contact details, then the property location. Tell us whether the land is vacant, farmed, used by a business or occupied by tenants. Mention an existing electric service, solar installation or land agreement if relevant.

Say whether you would consider a lease, sale or a defined part of the property. Acreage and parcel numbers can follow when available. You do not need a utility application or a completed site plan for an initial discussion.

An inquiry does not establish capacity or commit you to a project. Further review must address the actual connection, land rights, layout, approvals and commercial terms.

Questions landowners ask

Does SMECO’s solar map qualify land for a standalone battery?

No. Ask for review of the actual connection, charging and export operation. A solar map alone does not establish battery capacity.

Does limited export guarantee approval?

No. SMECO describes a request and review process for specified denied applications. Ask which conditions apply to the actual proposal.

Must my existing electric account serve the battery?

Ask the developer whether it proposes an existing-service arrangement or a separate project connection and account. Clarify who pays the associated charges.

Sources & further reading

Sources checked 2026-10-04. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in Maryland?Tell us about your land