Read the selection and its conditions together
The Maryland Public Service Commission selected Chalk Point, 400 MW in Prince George’s County, and Jade Meadow III, 40 MW in Garrett County, for conditional transmission-storage awards. The Commission says both must still apply for construction approval. It also expects a second-round application request by January 1, 2027.
For an owner, the useful distinction is between being selected for a revenue award and being authorized to build. Ask the developer to identify what its latest decision establishes. If it refers to another project, ask why that record matters to the property you are discussing.
Reference: Maryland PSC: October 1, 2026 conditional transmission-storage awards

Use the award milestones to ask about your own timeline
Order 92667 requires the selected projects to respond within 30 calendar days about accepting the standard obligations or proposing changes. Appendix A generally requires a construction application within 90 calendar days of acceptance or conditional acceptance, subject to a consensual extension. Those are project obligations, not a deadline for a landowner to sign.
Request the acceptance filing, current construction application reference and any extension decision if a developer relies on this award. A schedule in a presentation may have been prepared before the decision. Ask which dates have changed and what remains uncertain.
Compare those dates with your option agreement. Ask how long the property would be reserved, what an extension costs and who can request it. If a project misses a milestone, discuss the effect on your land rights separately from the consequences for its state award. Neither an award nor a missed deadline automatically rewrites your agreement.
Reference: Maryland PSC: Case 9866, item 117, Order 92667 and Appendix A standard obligations
| Project record | Question for your land agreement |
|---|---|
| Award conditions accepted | Has the team accepted them or requested changes? |
| Construction application | Which filing covers the actual battery layout? |
| Schedule extended | Does your option extend too, and on what terms? |
| Project cannot proceed | How are entry rights, recorded documents and damage resolved? |
Ask who a bond protects
Appendix A’s commercial-operation bond names the Commission as sole beneficiary and addresses ratepayer compensation for unexcused delay. A separate section addresses removal security. A developer’s reference to a state bond does not establish that it covers your rent, property damage or restoration rights.
Ask to see the actual security documents relied on for the proposal. Identify the beneficiary, covered obligations, expiration or cancellation provisions and the event that permits a claim. Have your adviser compare those documents with the promises in your agreement.
Keep payment protection and removal protection understandable on their own. Who pays if rent is overdue? Who repairs damage from investigation? Who funds removal after a failed or abandoned project? Ask which company remains responsible if the project is sold, and keep its current contact information.
A bond amount quoted for another project is not a proposed land payment. Nor is a state revenue-payment arrangement an account reserved for a landowner. Ask for the documents supporting any claim that your own payments are protected.
Reference: Maryland PSC: Case 9866, item 117, Order 92667 and Appendix A standard obligations
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landFind out which storage route is being proposed
Maryland’s PSC resources distinguish transmission procurement from the state’s 150 MW goal for distribution-connected, front-of-the-meter storage. Distribution company plans have their own review track. A smaller connection to a local utility system is not automatically part of the same competition as a large transmission project.
Ask whether the battery would serve the grid through a separate connection or operate with an existing building’s electric service. Request the utility name and proposed connection point. If the explanation changes between conversations, have the developer clarify the current design before you compare offers.
Reference: Maryland PSC: distribution storage and construction approval resources
For a utility proposal, ask which decision covers the project
In Order 92281, issued April 8, 2026, the PSC authorized BGE, Pepco, Delmarva Power and Potomac Edison to issue requests for proposals for their storage plans, subject to conditions. It deferred final project approvals until confidential pre-award conferences informed by the bid responses. Permission to seek bids is therefore different from approval of a named project.
If a developer describes a utility program as approved, ask for the utility name, procurement name and the record for the particular project. Is the company preparing a bid, responding to a request for more information or discussing a proposed selection? Ask for an update that identifies completed work rather than only the program announcement.
A battery on a business property also needs a clear explanation of its purpose. Would it serve your building, provide services to the electric grid or do both? Who would own the equipment and decide when it charges or discharges? Do not assume that hosting equipment includes backup power or a lower electric bill. Ask for any promised building benefit to be described in the actual design and agreement.
Separate the project’s utility contract from the land agreement offered to you. The project company may be paid for grid services while you receive rent for a defined area. Ask who owes your payment, what triggers it and whether your payment depends on the project receiving money from someone else.
If selection is still pending, ask how the company would report progress during an option period. Agree on the records you need to understand the next decision, while recognizing that confidential bidding materials may not be available to you. A short, dated project update can still identify the stage and remaining work.
Reference: Maryland PSC: Case 9715, Orders 92281, 92467 and 92537 on distribution-storage procurement
| Record or statement | Owner question |
|---|---|
| Utility plan approved | Does this authorize bidding or approve this particular project? |
| Bid submitted | Has the company been selected, and what remains under review? |
| Project selected | Which construction and connection decisions are still needed? |
| Land payment offered | Who owes me money and when does it start? |
| Battery on business property | Does the design actually provide any benefit to my building? |
Development funding does not settle your costs
The PSC’s June 9 Order 92467 denied an expedited request by the Exelon utilities to defer early development costs into a regulatory asset. The July 22 Order 92537 then conditionally approved tracking those costs, with requirements for issuing RFPs, preparing adequate pre-award analyses and keeping costs within specified limits. These decisions concern utility program development; they do not establish a landowner payment or approve a site.
For an owner, the practical question is who pays for each step before construction. If a developer wants surveys, soil tests or access improvements, ask which company orders and pays for that work. Would you be expected to contribute, reimburse costs or sign an application? Have those responsibilities explained before work begins.
Keep the cost of restoring investigation areas in the discussion. Ask who repairs a damaged track, fills test holes or restores drainage, even if the project is not selected. Identify who handles a complaint and what happens if the company arranging the work changes.
If a company says a funding decision will delay the project, ask which decision it means and how that affects the next agreed milestone. Compare the answer with your reservation period. Does an extension require your consent, change your payment or keep more land unavailable? A utility’s development schedule does not by itself explain your private agreement.
Request the current procurement documents before relying on a bid date or eligibility claim. These dated orders do not tell you whether a particular bidding window is open today. You can still send Sunland your property location and contact details without registering as a bidder or reserving your land.
Reference: Maryland PSC: Case 9715, Orders 92281, 92467 and 92537 on distribution-storage procurement
Ask which funding program the offer depends on
Maryland Energy Administration’s Megawatts for Maryland page describes anticipated grants to project developers, including standalone storage. As checked October 6, 2026, it presents a notice of intent and anticipated application stages. Its linked information request says final parameters and instructions will be in a funding announcement. These documents do not establish an open final application window or an award for a particular parcel.
If a company refers to this program, ask for the current announcement and the actual project application or award. Is it relying on anticipated funding, a preliminary eligibility response or a final grant? Have the company name the record supporting its answer.
Keep this MEA program separate from the PSC capacity-credit selection discussed above. Ask which support the proposed project expects to use and which parts of its financing remain unresolved. A program name alone does not explain whether the land offer can proceed.
Discuss your option while funding is unresolved. What are you paid during the reservation, how long can it last and what happens if funding is delayed or refused? Ask whether any proposed extension changes the payment, area or entry rights.
If you are asked to sign funding paperwork, request the full document and an explanation of your role. Would you be agreeing only to land access or taking on a separate obligation? Have that question resolved before signing. Your land payments should be understandable in the agreement you are offered.
Reference: Maryland Energy Administration: Megawatts for Maryland, current notice of intent · Maryland Energy Administration: May 2026 Megawatts for Maryland information request, not a final funding announcement
Ask what is ready and what is still being studied
A proposal should make the sequence understandable. Ask about the electrical application, site layout, land-use review and any procurement application. Identify which records already exist and which are only expected.
You do not need to interpret an engineering report alone. Ask the developer to explain its conclusion, its date and any conditions. A study that concerns a different site, connection or project size may not answer the question for your land.
- What is the project name and application reference?
- Which connection is being studied?
- Which decision is needed before construction?
- What might change the footprint or schedule?
Keep your reservation period understandable
If the developer needs an option before an award or approval, ask what work it can perform on your land during that period. Find out what you are paid, who can extend the option and what ends it. Identify any activities you must postpone while the land is held.
Ask how investigations are scheduled and how damage is handled. If a tenant, farm operator or neighbor uses an entrance, explain those rights before agreeing to entry. A possible future project does not make existing access arrangements disappear.
Your land payment is not a capacity-credit price
A project may receive payments for providing energy or grid services. Your compensation depends on the land agreement. Do not compare a project’s per-MW revenue figure directly with annual rent per acre; they describe different things.
Request a land-payment schedule with the reserved area, option period, operating start and any increases or extensions. Include access, restoration and removal responsibilities in the comparison. Ask what happens if the operator or project owner changes.
Send what you know about the property
Start with your contact details and the location. Include the present use, approximate available area and whether you are considering a lease, sale or only a discussion. Mention a received offer or application reference if you have one.
You can inquire without a completed electrical study or a state award. Sunland can review the starting information and may ask for more detail. We still need to establish property-specific suitability and commercial interest before there is a deal to consider.
Questions landowners ask
Does a conditional award permit construction?
No. The October 2026 announcement says the selected projects still need to apply for construction approval.
Does an award in my county mean nearby land is being sought?
No. It concerns specified projects. A separate property needs its own review.
Do smaller distribution projects follow the same procurement?
Do not assume that. Ask which utility plan, program and approval route apply to the proposal.
Does approval of a utility storage plan mean my project was selected?
No. Order 92281 authorizes RFPs subject to conditions and defers final project approvals to later review. Ask for the record for the particular project.
Will a battery on my business property provide backup power?
Ask for the actual design and written commitment. Hosting a grid-service battery does not by itself explain how it would serve your building.
Sources & further reading
Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.
- Maryland PSC: October 1, 2026 conditional transmission-storage awards
- Maryland PSC: Case 9866, item 117, Order 92667 and Appendix A standard obligations
- Maryland PSC: distribution storage and construction approval resources
- Maryland PSC: Case 9715, Orders 92281, 92467 and 92537 on distribution-storage procurement
- Maryland Energy Administration: Megawatts for Maryland, current notice of intent
- Maryland Energy Administration: May 2026 Megawatts for Maryland information request, not a final funding announcement