Understand the county’s role and stated concerns
The county’s workgroup page describes projects under consideration by the Maryland Public Service Commission. It includes county departments, fire-company representatives and community participants, and reports environmental and public-safety concerns.
This is the county’s description of its workgroup, not a determination about your parcel. Ask the project team which state and local decisions apply to its design and how it intends to address questions from officials and neighbors. Do not assume that a state filing makes every local issue disappear.
Reference: Harford County: community solar and battery storage workgroup

Ask for case documents rather than a presentation alone
The county’s Conastone/Oystercatcher page links to a PSC case filing and organizes community presentation, advocacy and hearing material. A presentation explains a proposal; it is not the same document as a final approval or its conditions.
If someone cites this project as evidence for your land, ask for the relevant decision and what it actually covers. Request the name, filing reference and current stage of the proposal involving your property. Do not use the presence of a public project page as proof that it is operating or that your land qualifies.
Reference: Harford County: Conastone/Oystercatcher project records
Check what the latest award decision actually says
The October 1, 2026 PSC decision did not select Oystercatcher for a first-round energy storage capacity-credit award. Order 92667 invites its applicant, Cardinal Energy Storage East, to participate in Round 2. An invitation is not a later award or permission to build.
If someone uses the project as an example when approaching you, ask which dated record supports the statement. Keep a revenue-award decision separate from construction approval, a completed electrical study or a signed land agreement. None should be assumed from a project name in a presentation.
For a proposal involving your land, ask whether the developer expects to bid again, use another commercial route or stop work. Compare that answer with the option period and extension rights being requested. A possible later competition is a reason to discuss the reservation period, not a general deadline for owners to act.
Discuss what happens if the developer changes plans. Ask whether you would receive written notice, what payments continue and how recorded rights would be released if the project ends. Those answers belong in the proposed agreement rather than being inferred from a state procurement decision.
Reference: Maryland PSC: October 1, 2026 award decision · Maryland PSC: Case 9866, item 117, Order 92667
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landCompare the land reservation with the connection schedule
PJM’s June 3, 2026 Phase II study for Conastone AH1-725 describes preliminary connection work and estimates a 42–72 month installation period after both a signed interconnection agreement and a construction kickoff call. It assumes permits, environmental issues and scheduled outages do not delay the work. That is a conditional estimate for one project, not a countdown from the study’s publication or a schedule for your land.
For an offer on your property, request the current connection schedule and the event that starts it. Then put it beside the proposed option end date, extension payments and date full rent would begin. A developer may need years to arrange a connection; you still need to know what you would receive while the land is reserved.
Ask which rights continue during that wait. For example, could you renew a farm tenancy, replace a building or sell part of the property? Have the agreement address delayed milestones and notice of a changed schedule. An expected construction year should not leave the length of your commitment unclear.
Reference: PJM: Conastone AH1-725 Phase II study, June 3, 2026; connection scope and timing
Draw the connection route as well as the battery site
The same dated study describes a gas-insulated connection extending roughly half a mile from the substation to a developer-provided ownership boundary. Its cost findings are preliminary, and the developer remains responsible for actual construction costs. The equipment pad is only part of the physical proposal.
Ask for a drawing that separates the leased area, permanent connection rights and temporary work areas. Identify any strip crossing land you intend to keep, along with gates, drainage crossings and access for repairs. Confirm who would hold each right and whether a separate document would be recorded.
If the route changes after you sign, ask how your consent, compensation and restoration would be handled. Do not assume a payment for the battery pad also covers an additional route. The current project documents and proposed agreement must settle that question for your property.
Reference: PJM: Conastone AH1-725 Phase II study, June 3, 2026; connection scope and timing
Have the owner’s place in the process explained
Ask who would communicate with agencies and neighbors, what may be said about your land and which filings require owner authorization. Keep copies of drawings and documents you approve. A conversation about leasing does not by itself authorize a developer to submit a petition in your name.
Discuss how material changes would reach you. A larger footprint, different entrance or new cable route can affect land you planned to retain. Ask who reviews those changes with you and how commitments made during public review would become operating responsibilities.
Check current zoning separately from another case
Harford County’s zoning administration page links to its code, use charts and development-regulation updates. Ask the responsible office which current provisions and jurisdiction apply to the actual parcel and proposed battery.
Provide the parcel location and municipality if known. Existing solar, agricultural or industrial use should be described accurately rather than taken as automatic permission for storage. If the team expects a state construction review, ask which local permits, plan reviews or other steps still need to be addressed.
Reference: Harford County: zoning administration and regulation updates
Get concrete answers about access and operations
Request a plan showing equipment, entrances, cables, screening and construction space. Mark nearby buildings, drainage and paths needed for your current use. Ask where deliveries and servicing would occur and what arrangements are proposed for emergency access.
Find out who maintains the site, responds to an incident and updates the operating plan after a transfer. Ask which studies support any statements about noise or other effects on the property. Review removal, restoration and payment responsibilities with the land agreement rather than relying on a community slide.
An inquiry can start with incomplete information
Send Sunland your contact details and property location. Add Harford County, municipality, current use and utility if known. Mention any offer, case number or project name someone has given you; property details beyond the required location remain optional.
You do not need to settle an approval dispute or hire a designer before contacting us. Further investigation must establish the current route, connection, layout and commercial fit. An inquiry is not support for a particular public application or a commitment to lease or sell.
Questions landowners ask
Does the county project page prove final approval?
No. Check the actual decision, current status and conditions in the relevant case.
Does a nearby proposal mean my land is needed?
No. A separate property needs its own connection, rights and commercial review.
Does contacting Sunland authorize a public filing?
No. An initial inquiry does not authorize representation or a petition on your behalf.
Sources & further reading
Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.
- Harford County: community solar and battery storage workgroup
- Harford County: Conastone/Oystercatcher project records
- Harford County: zoning administration and regulation updates
- Maryland PSC: October 1, 2026 award decision
- Maryland PSC: Case 9866, item 117, Order 92667
- PJM: Conastone AH1-725 Phase II study, June 3, 2026; connection scope and timing