Prince George’s County, Maryland

Battery storage land in Prince George’s County, Maryland

What the Chalk Point storage award means for Prince George’s County landowners, and what to check before considering a battery lease.

Could my land work?

Chalk Point’s conditional award concerns a specific existing power-plant site. It does not tell you whether nearby land is needed or suitable. For your property, start with the proposed use, the electrical connection and a layout showing the rights a developer would need.

Chalk Point is a project-specific award

The Maryland Public Service Commission conditionally selected the 400-megawatt Chalk Point Storage Project in Aquasco on October 1, 2026. Its announcement places the proposal at the existing Chalk Point power plant. Construction approval remains a separate step.

An award for that site is useful context, but it is not an invitation to lease all land around it. If someone mentions Chalk Point while discussing your property, ask whether they are working on that project or proposing something separate. Ask what part of your land they need and why.

Reference: Maryland PSC: October 1, 2026 conditional transmission-storage awards

Model landscape illustration of battery enclosures, an electrical substation and a proposed site layout.

Get an answer about the actual proposed use

The Planning Department provides PGAtlas for parcel zoning and development information. It also describes a written Zoning Ordinance Interpretation process for owners or others with a contractual land interest, including questions about unlisted uses and approval conditions.

A map can help identify a zone; it does not explain every part of a battery proposal. Give the planning office a clear description of storage alone, storage with solar, or equipment serving an existing operation. Ask which process applies to this parcel and design before agreeing to a schedule.

Reference: Prince George’s Planning Department: parcel information and written zoning interpretations

Find out what rights are already on the property

If the land has hosted energy equipment or an industrial operation, collect the agreements you already have. Ask who controls access, existing cables and any space promised for future expansion. A new developer should explain how its proposal fits those rights rather than assume that ownership of the land resolves them.

For land next to an existing facility, draw the boundary between your property and the project site. Ask whether the offer covers battery equipment, a cable route, access or more than one of those uses. Different uses can affect different portions of the land. Keep the area you intend to retain visible on the plan.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Ask for connection evidence you can understand

A proposed connection needs a location and an explanation of the work still outstanding. Ask whether the battery would connect to a transmission facility or a local distribution circuit, and which studies or agreements cover charging and export. Being near an existing power plant is not the same as having permission or capacity to connect.

Request a plain-language account of the next electrical decision, who pays for it and what could change the plan. If the cable must cross other land, ask who obtains those rights. You should not have to infer the route from an aerial photo or a reference to a large nearby project.

Check that the documents describe the same proposal

PJM’s June 3, 2026 Phase II study for Chalk Point, request AH1-552, describes a larger studied proposal than the 400-megawatt October award. The documents serve different purposes. Their figures should not be combined into a claim about today’s approved project or available capacity for another property.

If a company gives you several records, ask it to identify which proposal each one covers. Compare the company name, project reference, date, equipment and drawing. Ask what changed between versions and which record supports the rights it wants from you now.

Keep the latest drawing with the proposed land description. If an earlier study covers a different size or arrangement, ask what further work is needed for the revised plan. You do not need to resolve the engineering yourself; the project team should explain the difference and provide the supporting record.

Reference: PJM: June 3, 2026 Chalk Point AH1-552 Phase II study, scope and connection-work assumptions · Maryland PSC: October 1, 2026 conditional transmission-storage awards

Read the starting point behind a promised schedule

The June study estimates connection work after a signed connection agreement and a construction kickoff call. It also assumes permits, environmental matters and required outages do not delay that work. This is a dated estimate with conditions, not confirmation that those steps have happened or a guaranteed date for land payments.

For your offer, request a dated schedule that names the event starting each period. If the company says work takes a certain number of months, ask: months from what? Mark the steps already completed and those still waiting on another decision.

Compare that schedule with the option deadline and rent trigger. What do you receive while the company waits to start the connection work? If the option would expire first, ask what a paid extension would cost and how unused land would be released. Put the agreed dates and payments in the land documents.

Before accepting a revised schedule, ask which assumption changed and how it affects your property. A later utility milestone should not leave you guessing about access, current uses or the amount owed during the wait.

Reference: PJM: June 3, 2026 Chalk Point AH1-552 Phase II study, scope and connection-work assumptions

Compare the land agreement with your plans

Before reserving land, ask what the developer can do during the option period. Understand entry for investigations, payments, extensions and the date your property is released if the project does not proceed. If you already have a tenant or another offer, explain that before discussing exclusivity.

For a lease, ask what starts rent, which areas can be used temporarily and which remain occupied during operation. Include removal, restoration and responsibility for damage in the review. Have the agreement reviewed for your circumstances before signing. A headline payment does not explain how much land or flexibility you would give up.

Send the location and the question you want answered

Use the form to send Sunland your contact details and property location. Add the current use, parcel reference, utility and any project name if known. Say whether you are considering a lease, sale or simply want to learn whether storage is worth investigating.

You do not need to complete a planning application or choose a battery size first. We can start with the information you have. Further review needs to establish the rights, layout, connection, approvals and commercial fit. Contacting Sunland does not reserve the land or authorize a filing on your behalf.

Questions landowners ask

Does Chalk Point’s award approve my land for storage?

No. It concerns a particular proposed project at an existing power-plant site.

Can a zoning map settle whether batteries are allowed?

It identifies the mapped zone. Ask the responsible office about the actual use and design.

Should I send an offer I have already received?

You can mention it in your inquiry. It helps explain the rights and deadlines you are considering.

Does a connection-work estimate tell me when rent begins?

Your agreement sets the rent trigger. Ask when the estimate’s clock starts, which steps remain and what you receive while the company waits. Keep those answers in the land documents.

Sources & further reading

Sources checked 2026-10-07. Local rules and program details can change. Check the requirements for the actual project.