Dominion Energy / Virginia

Battery storage land in Dominion Energy’s Virginia service area

What Virginia landowners should ask about Dominion’s generation maps, the applicable connection process and land needed beyond the battery equipment.

Could my land work?

A distribution-line connection does not automatically mean a state-only review. Dominion explains that some distribution requests involve PJM, while transmission connections also have utility requirements. Ask which route the actual proposal uses and what evidence supports it.

Ask who is reviewing the actual proposal

Dominion’s Virginia interconnection page distinguishes state and federal jurisdiction. It says federally governed requests go through PJM, including some distribution connections. It also identifies utility requirements for transmission connections.

Ask the developer to name the reviewing organizations and describe their roles. Do not decide the process from the equipment size or a line’s appearance. A useful answer identifies the proposed operation and connection point, not just a promise that the land is near power.

Reference: Dominion Energy Virginia: parallel generation and interconnection

Model landscape illustration of battery storage sites and an electrical substation connected by roads and power lines.

A solar-oriented map is not a battery study

Dominion describes its hosting tool as guidance for solar siting and says an interconnection study is needed to confirm map information. Its published exclusions include industrial and network feeders, and projects not yet connected are not included in the analysis.

If a developer cites a favorable map color, ask how battery charging was evaluated and what later study is required. If a line is absent from the map, ask why; do not treat absence as a definitive rejection. Neither result establishes the final design or cost.

Reference: Dominion Energy: hosting capacity tool and exclusions

A project buyer may need rights beyond the battery area

Dominion’s current acquisition directory includes standalone storage and says acquisition proposals are accepted continuously. Its 2026 RFP evaluates land control across the project, including off-site rights and drainage routes. It also calls for purchase rights where a transmission switchyard is needed. A project purchase is separate from a landowner payment.

Ask the developer to identify the procurement route and show every affected area. Which parts would be leased, purchased or covered by an easement? Does the offer include a switchyard or land outside the battery enclosure? Request the proposed document for each right.

Tell the team which uses you need to keep. Compare any sale area with the access and drainage rights required for retained land. Discuss when each transaction would occur, how it is paid for and what happens if the project changes.

If the proposal depends on a future project acquisition, ask who signs your agreement and who remains responsible before and after the transfer. Keep the buyer’s project review milestones separate from the conditions that start your own payments.

Reference: Dominion Energy Virginia: current acquisition and power purchase solicitation directory · Dominion Energy Virginia: 2026 development asset acquisition RFP, section 7 land agreements

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Include land outside the enclosure in the discussion

A battery proposal may need an entrance, a cable route and other electrical facilities beyond the equipment area. Request a drawing that separates permanent land use from temporary construction space and identifies any route across neighboring land.

Before discussing an annual payment, understand all the rights being requested. Ask whether the project would limit building, planting, driving or other activity outside the fenced area. Explain the access and uses you need to keep.

Keep the land-use review on the list

An electrical application does not settle the local approval of the property use. Provide the county, city or town and parcel number if known. Ask who handles the land-use application and what is needed for the actual storage proposal.

Have the developer explain sound, drainage, emergency access and removal in terms of the site drawing. If these depend on later engineering, ask when the design will be available and what choices remain open to you before a lease starts.

Ask how studies affect the option timeline

If a project needs several reviews, find out which work happens first and what evidence you will receive. Ask who pays for studies and upgrades. Have the developer explain what happens to the reserved land if the expected route cannot be used.

You can contact Sunland before any studies are complete. Send the location, current use and utility if known. Mention a prior proposal or application reference if you have one. An inquiry begins an investigation; it does not promise Dominion or PJM approval.

Questions landowners ask

Does a distribution connection always avoid PJM?

No. Dominion states that some distribution requests involve federal jurisdiction and PJM. The actual request determines the process.

Can I rely on a solar hosting map to qualify a battery parcel?

No. Ask about charging, export, map limitations and project-specific studies.

Is the battery enclosure the only land affected?

Not necessarily. Ask for access, cable routes, other electrical facilities and construction space to be shown.

Sources & further reading

Sources checked 2026-10-04. Local rules and program details can change. Check the requirements for the actual project.

Want to ask about your land?

Send the location and what you know about the property. You don’t need a project plan, and you are not committing to a lease or sale.

Tell us about your land
Have land in Virginia?Tell us about your land