What the September awards tell you
NYSERDA announced eight contracted bulk-storage projects in September 2026, totaling 950 MW once operating. The announcement says project payments begin after commercial operation and required approvals. It also describes another bulk solicitation planned by year-end. These are development commitments, not proof of operating equipment or an offer for nearby land.
If someone refers to this announcement in an approach to you, find out whether they represent an awarded project, a future bidder or a separate proposal. Request the project name. A developer should be able to explain the connection between its plans and the announcement without implying that your parcel is already approved.
Reference: NYSERDA: September 2026 bulk-storage awards

Your payment dates need their own explanation
A land offer may include an option payment now and operating rent later. Read what triggers each payment. Does rent begin on a fixed date, on construction, on commercial operation or on another event? Write the trigger next to the amount so the schedule is understandable.
If the developer’s project revenue begins later than your payments, ask how the earlier obligations will be met. If your rent waits for project operation, understand what you receive during the wait and how long that wait can last. Do not assume the state project-payment date and your lease-payment date are the same.
| Record | Date or condition to identify |
|---|---|
| Option | Start, expiration and extension rights |
| Land payments | Trigger for each stage of compensation |
| Project award | Conditions and delivery obligations |
| Construction | Approvals and connection work still needed |
Read a future bid as a future bid
Before a developer has won a contract, its proposal may depend on being selected later. Ask which solicitation it expects to enter, what work will happen first and what would change if the bid is unsuccessful. Keep the uncertainty visible in the option period.
Ask when the land is released if the developer stops pursuing the bid. If the agreement allows several extensions, total the possible reservation period and the payments for each extension. Consider that full period against your plans to farm, sell, build or lease to someone else.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landWhy a bidder may ask for signed land rights
The first solicitation, ISCRFP25-1, required executed site control for the proposed footprint through specified agreements, including a binding option, lease or purchase, plus a reasonable connection plan. This is a historical requirement, not a confirmed rule for the planned second round.
If a developer says it needs your signature to bid, ask which solicitation it means and which document it wants signed. Request the relevant requirement and a plain explanation of the rights the agreement grants. A deadline does not explain the price, reservation period or limits on your use.
Read the agreement with its attachments. Which land is reserved, when does the reservation end and what can the developer do before exercising the option? Does it allow testing, applications, recording a notice or assigning rights to another company? Ask your adviser to explain these provisions before signing.
Keep a copy of the completed document and the drawing you reviewed. If the company changes the layout or asks for a longer hold, compare the request with that original record. Discuss payment and release terms for any additional commitment rather than treating it as paperwork for the same bid.
Reference: NYSERDA: ISCRFP25-1, November 10, 2025 update, site-control and permitting requirements
Match the land agreement to the whole connection route
The first RFP requested site-control information for project rights-of-way and the connection point, and maps aligned with the submitted parcel and project boundaries. Its evaluation favored rights secured beyond the equipment footprint where applicable.
Ask the developer to show the route from the battery area to the proposed connection. Which parts are on your property? Which cross other land? Mark the areas covered by signed agreements separately from routes that remain only proposals.
If your land is needed for a cable or entrance rather than the batteries themselves, ask for an offer that describes that role. What construction is allowed, who may enter afterward, and can you still farm, build or cross the route? Keep temporary work space separate from permanent rights.
Discuss what happens if the preferred route is unavailable. Could the company request more of your land, move the entrance or delay the project? Ask how you will review changes and when unused rights must be released. A bid map should not leave the final extent of your commitment unexplained.
Reference: NYSERDA: ISCRFP25-1, November 10, 2025 update, site-control and permitting requirements
| Document or drawing | Owner question |
|---|---|
| Signed land agreement | What rights have I granted, and for how long? |
| Project footprint | Which area is actually reserved? |
| Connection and access routes | Which rights exist and which remain unresolved? |
| Revised proposal | What changes require my review or further agreement? |
Use the right round when discussing a deadline
NYSERDA’s current solicitation page says it intends to issue the second bulk-storage solicitation by the end of 2026. The first RFP’s deadlines have passed. Its conditions should not be presented as an issued second-round offer.
Ask the company to identify the round in writing. If it is preparing for a future solicitation, what work will it carry out before the final requirements are available? If it represents an already contracted project, which project is it and why does it need this additional land?
Request a short progress schedule tied to your agreement: expected bid, decision, permit and connection milestones; when the company will update you; and the outside date for releasing the land. Keep your payment schedule beside it.
If the next round changes or arrives later than expected, ask which extension rights the company could use. Would extra time be paid, and could you decline an additional hold? Consider the longest possible reservation against your own plans for the property.
Reference: NYSERDA: bulk-storage solicitations and planned second round · NYSERDA: ISCRFP25-1, November 10, 2025 update, site-control and permitting requirements
Use the project resources to prepare for local discussions
NYSERDA’s bulk-storage program page provides a host-community webinar covering local planning, zoning and fire-safety considerations. These resources can help you prepare questions. They do not establish what your municipality has decided about a particular application.
Give the developer the actual town, village or city and parcel reference. Ask which office will review the proposal and which drawings will be supplied. If your home, a tenant or a shared entrance is nearby, make sure it appears in the discussion rather than leaving it out of a large-scale project presentation.
Reference: NYSERDA: bulk energy storage program and host-community resources
The connection route belongs in the land offer
Ask where the battery would connect and how the route reaches that point. Equipment on one parcel may need cables or access across another. Identify whether those rights already exist, remain to be negotiated or depend on someone else’s agreement.
The map attached to your documents should show permanent and temporary areas separately. Mark the uses you want to retain. If studies may move the equipment or route, find out how changes would be approved and whether additional affected land changes the compensation.
What to send for an initial review
Send the property location and your contact details. If you have received an offer, mention the named project, the proposed use and any dates the developer has given you. Include the area you might offer and current use if known.
You can ask about the land before there is a bid, project size or completed study. Sunland can begin with your property information and may follow up. A review still needs to establish commercial interest, connection, layout and approvals before anyone can offer a workable deal.
Questions landowners ask
Does a NYSERDA award determine my lease payment?
No. Your option or lease needs its own payment amounts, dates and conditions.
Does an awarded bulk project still need approvals?
Yes. The September announcement says project payments follow commercial operation and required approvals.
What if the developer expects to bid later?
Identify the bid dependency, option payments, full reservation period and release terms if the bid fails.
Why would a developer need land rights before a bid?
The first solicitation required specified executed site-control agreements. Ask which round and document the company means, and review the rights, payments and reservation period before signing.
Are first-round requirements confirmed for the next round?
No. NYSERDA says it intends to issue the second solicitation by year-end 2026. Check that round’s actual documents when available rather than treating the first RFP as its final rules.