Confirm electric service rather than a familiar company name
Use the electric utility on an existing bill. A company providing gas to the property is not by itself evidence of which utility handles the proposed electric connection. If there is no meter, include the location and note that service is unknown.
Ask whether the battery would be associated with a building’s account or use a separate grid connection. Mention existing solar or other equipment and any tenant who controls the service. A design using someone else’s account needs that arrangement explained.

The resource list helps separate different questions
RG&E’s DG page links to a hosting-capacity portal covering PV, BESS and electrification, a project queue, upgrade disclosures and capital-upgrade resources. It provides a dedicated contact for storage connections and rates.
Those resources are not interchangeable. Ask what the developer learned from each and what remains to be confirmed for the actual design. If it only looked at the queue or map, have that described as early research rather than a finished engineering or cost review.
Reference: RG&E: interconnection, storage, queue and upgrade resources
A queued project is not capacity assigned to you
If someone points to another battery application near your land, request the project reference and explain what connection it concerns. Nearby projects can be useful context, but their studies, rights and costs belong to their own proposals.
Ask for your project’s application stage and connection point. Do not assume the closest visible substation is the intended point. If several alternatives are being considered, find out when the choice is expected and whether it changes the land area or route requested from you.
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAsk what shared upgrades would mean for this offer
A discussion may include utility work that also benefits other projects. Ask whether a quoted cost is a preliminary estimate, a project-specific assessment or an amount dependent on other participants. Identify who pays and which conditions could change the number.
If the developer expects another project or upgrade to move ahead first, ask what evidence supports the schedule. Your land reservation should explain what happens if that dependency is delayed or does not occur. A shared-upgrade label does not itself make a cost or completion date certain.
| Item | What to clarify |
|---|---|
| Connection point | Chosen location or alternative under review? |
| Upgrade cost | Estimate, assessment or conditional share? |
| Dependency | What other work must happen first? |
| Land reservation | Payment and release terms if work is delayed? |
Read the upgrade estimate before relying on the headline
RG&E’s September 17, 2026 disclosure separates planning-grade estimates, incremental hosting capacity, percentage received and milestone schedules. Some substations have several upgrade rows. The schedule footnote warns that material lead time may affect timing. These fields describe different parts of the utility work; they do not establish a complete connection for your land.
Ask the developer to identify the exact upgrade behind its proposal. Is it a line, transformer or another item? If it names a substation, ask which rows matter and whether other work is still needed. A price beside one row may cover only part of the proposed connection.
Do not read “percentage received” as the percentage of construction finished. Ask what has been received, who provided it and what remains due under the actual project records. A blank field leaves that information unstated. It does not mean the cost is zero or the work is ready.
Have the developer distinguish the published planning estimate from its own assessed costs. What is included, what is missing and who pays if the amount changes? The hosting-capacity figure also needs a project-specific explanation covering battery charging and export; it is not a reservation for your parcel.
Bring the answer back to your agreement. If higher costs could end the project, ask when that decision must be made and how your land is released. If the company can extend the option, compare the extension payment with the time and area you would continue to hold for it.
Reference: RG&E: qualifying upgrade disclosure, September 17, 2026
Check which work must finish before your land can be used
The combined NYSEG and RG&E work plan dated August 11, 2026 lists engineering, material and construction milestones, with project identifiers, for qualifying upgrades described as having reached mobilization thresholds. It is an older record than the September disclosure. A listed date or completed field is not proof that every task for an individual battery is finished.
Ask for a current schedule that ties each needed upgrade to the battery proposal. Which project numbers match the work being discussed? Has engineering finished, have materials arrived and has construction started? Request the latest record for each answer rather than treating an old forecast as a confirmed event.
For example, a developer may have a study for one upgrade while the project still needs line work elsewhere. Ask it to show those dependencies together. A completed equipment task does not settle another route, a crossing agreement or operating permission.
Compare those milestones with the dates in your option or lease. Does rent begin when the agreement is signed, construction starts or some later condition is met? What happens if utility materials arrive late but the developer wants to keep your land reserved?
Ask who must notify you when the schedule changes and which documents you can receive. Keep the dated schedule with your agreement so a later conversation has a clear starting point. Sunland’s initial inquiry only needs your contact details and location; you do not need to assemble these utility records yourself.
Reference: NYSEG and RG&E: qualifying-upgrade work plans, August 11, 2026
Keep billing discussions separate from land rent
The utility resource page also covers generation billing and metering. Ask which storage rate or compensation arrangement applies to the proposal. Do not infer battery revenue from a solar billing example or treat an electric-account credit as your land payment.
Your agreement should explain the compensation you receive, the land covered and the payment triggers. Review the option period, extensions, damage, restoration and removal duties together. If project ownership may change, identify how your obligations and payments would be handled.
Start with the information you already have
Send Sunland the location and contact details. Include the present use, approximate available area, electric utility and any received proposal if known. Mention a queue reference or upgrade discussion without guessing at its conclusions.
You do not need to calculate capacity or choose a tariff before asking about the land. Further work must establish the actual connection, layout, approvals and commercial fit. An inquiry does not create an application or reserve electrical capacity.
Questions landowners ask
Does another queued battery qualify my parcel?
No. It concerns another proposal; your connection and land need their own review.
Does RG&E gas service establish electric service for a battery?
No. Confirm the electric utility and actual proposed connection.
Are utility billing credits the same as land rent?
No. Your land compensation is governed by the land agreement, separate from project billing.
Does “percentage received” mean an upgrade is that far through construction?
No. The disclosure gives that field separately from milestone schedules. Ask the developer what the received amount represents and obtain current engineering, material and construction records for the work its proposal needs.
Does a completed utility upgrade mean a battery on my land can operate?
It does not establish that by itself. Match the specific work to the proposal, identify other required upgrades and routes, and confirm the remaining agreements and operating permission. Review your land-payment triggers separately.
Sources & further reading
RG&E resource-page body and selected storage and interconnection panels checked October 7, 2026. The September 17 qualifying-upgrade disclosure and August 11 combined work plan were read in full, including their dates and column headings. Appendix E of the SIR, individual studies, current construction status and project-specific agreements were not reviewed. Confirm current scope, costs and milestones for the actual proposal. Local rules and program details can change. Check the requirements for the actual project.