Keep the location and electric service together
Send the municipality, county and address or road. Include the electric utility on an existing bill if known. For land without service, explain that rather than choosing a utility from a nearby building.
This guide concerns New York property. Have the project team confirm the actual state, utility and process before relying on a regional company name. A proposed cable route may need rights away from the equipment site, so include the parcel and intended connection in the discussion.

What queued and connected mean
Orange & Rockland describes queued generation as an approved connection application still in progress. Connected generation has permission to operate. Those labels establish different stages; a queued entry is not evidence that equipment is operating.
If a developer refers to a nearby entry, ask for the reference and explain how it relates to your own proposal. Is it another project, a possible constraint or evidence of an application for the battery being discussed? Do not assume the neighbor’s application assigns capacity to your parcel.
Reference: Orange & Rockland: hosting capacity and queue definitions
A missing map value leaves a question
The utility FAQ says its hosting maps cover feeders at 12 kV or above and that the values do not replace location-specific engineering under the connection requirements. A missing display should therefore lead to clarification of map coverage and service.
Ask which current storage resource and operating assumptions apply to the proposal. The cited FAQ is general hosting guidance; it does not establish a storage-specific acceptance for your land. A color, blank area or queue total alone is not enough to settle the project.
Reference: Orange & Rockland: hosting capacity and queue definitions
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landFind out what connection work is still missing
Request the application stage and intended connection point. Ask whether costs are preliminary, studied or dependent on a different design. If there is no application yet, have that stated clearly rather than described as an approved project.
If upgrades or other projects affect timing, ask what has to happen first. Compare that explanation with the time the developer wants to hold the land. The option should explain extensions, payments and release if the planned connection does not work.
Do not lose sight of the rest of the parcel
Show access you need for farming, buildings or future development. Request the equipment, entrance, cable route and temporary work areas on the same plan. Identify drainage or site features the developer needs to investigate rather than assuming all open space is usable.
Ask who handles neighboring rights and any work beyond the parcel. Find out whether the proposed reserved area can expand and how you would approve a change. You should be able to distinguish the final operating area from land used only during studies or construction.
An inquiry can start before the technical answer
Send Sunland your contact details and location. Add the current use, approximate area and electric utility if known. If an offer relies on a hosting map or nearby queue entry, mention that claim and its date.
You do not need to obtain utility approval before discussing your property. Further work must establish a usable layout, connection, approvals and commercial fit. The inquiry does not reserve capacity, enroll an account or commit you to a lease.
Questions landowners ask
Does queued mean a battery is operating?
No. The utility distinguishes an application in progress from permission to operate.
Does no map value rule out my property?
It leaves a question about coverage and service. Ask for the actual connection review.
Can a nearby approved application qualify my parcel?
No. Your proposal needs its own evidence.
Sources & further reading
Sources checked 2026-10-04. Local rules and program details can change. Check the requirements for the actual project.