PSEG Long Island / New York

Battery storage land on Long Island: connection questions

A guide for Long Island landowners to the local interconnection resources, town approvals and property questions a battery proposal needs to address.

Could my land work?

For a site connected to LIPA’s distribution system, start with PSEG Long Island’s local interconnection resources. Do not substitute a mainland utility’s map or process. The connection review and the rules adopted for the parcel are separate checks.

Start with the local interconnection resources

PSEG Long Island’s Small Generator Interconnection Procedures page provides the application portal, instructions, technical references, queue resources and hosting-capacity links for LIPA’s distribution system. Confirm with the utility which current route applies to the actual storage proposal.

Ask the developer to identify the resource used, the proposed connection point and the status of any application. A statewide reference or a mainland utility’s map cannot establish the conditions at a Long Island parcel.

Reference: PSEG Long Island: LIPA interconnection procedures and resources

Model landscape illustration of battery storage sites and an electrical substation connected by roads and power lines.

Find out what has actually been checked

A battery both charges and discharges. Ask what information the developer has supplied about those operating modes and which requirements the utility has reviewed. You do not need to choose equipment or an electrical rating to make an initial inquiry.

PSEG Long Island’s page describes a process running from planning and application through installation, inspection, testing and signoff. A submitted application is an early step, not permission to operate. Ask which steps and costs remain before anyone calls a site ready.

Reference: PSEG Long Island: LIPA interconnection procedures and resources

Include the town, village or city for the parcel

A county name or postal address may not identify the authority that handles land-use approvals. Include the municipality from your property records if you know it and say whether the parcel is within a village.

Ask that authority for the current battery rules, any restrictions on accepting applications and the review path for the actual proposal. Do not rely on an old moratorium article or a neighboring town’s decision. Record the answer and date before making commitments based on it.

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Read the owner consent before signing it

PSEG Long Island’s July 2026 Appendix H says the acknowledgment does not convey a property interest. It nevertheless asks the owner to certify either an exclusive working relationship with the developer or an executed option, lease or purchase agreement. Those statements deserve review; a form described as routine can still ask you to confirm something specific.

Check the project, address, company and selected statement against your records. Ask why this form applies to the proposed arrangement, particularly if your existing electrical facilities would be involved. Do not certify an agreement that remains unsigned or an exclusive relationship you have not agreed to.

Keep the completed form and supporting documents. Ask who will submit them and request a copy of the submission. Have your adviser compare the certification with your actual land agreement; the utility form does not supply your rent, extension payments or release terms.

Reference: PSEG Long Island: Appendix H, Property Owner Consent Form, revised July 2026

Check the agreement behind a site-control certificate

July 2026 Appendix H-1 certifies an agreement for construction and operation on the identified property. It provides choices for an option, lease, purchase agreement or exclusive license or other agreement, and asks for the agreement date and term, including extensions.

Compare the selected agreement and dates with the documents you signed. If an option has expired, a proposed extension remains unsigned or only part of the parcel is available, ask how the certification will accurately describe those facts. Do not sign a form because someone says the utility needs it quickly.

Ask the developer to identify the project number and explain what remains in connection review. A certificate about land rights does not establish that the utility has approved the battery. Discuss the release of unused land and recorded notices separately in your agreement.

Reference: PSEG Long Island: Appendix H-1, Site Control Certification, revised July 2026

Ask which battery operation the utility is studying

July 2026 Appendix J asks applicants to distinguish standalone and hybrid storage and describe charging, discharging, import demand and operating windows. It says circuit conditions determine final charging and discharging windows and rates. An equipment rating alone does not explain how the proposed system would operate.

Ask the project team to describe the submitted arrangement in ordinary language: where the battery gets electricity, where it sends electricity and whether operation is limited at certain times. Request the dated proposal and utility response. You do not need to prepare these engineering details before asking Sunland about your property.

If the team changes the battery or its operation, ask whether the utility must review the change and whether it affects the layout, schedule or requested land rights. Have any need for more equipment area or a different route explained before agreeing to it.

Reference: PSEG Long Island: Appendix J, ESS Application Requirements, revised July 2026

Small parcels need a clear drawing

Ask for equipment, access, utility routes and nearby buildings to be shown together. If you operate a business, mark the parking and deliveries you need to retain. If the land adjoins your home, explain which areas you want kept separate.

A compact battery layout does not remove the need to investigate separation, access and noise. Ask what the proposed design assumes about neighboring land and whether any rights outside your parcel are needed. Do not agree to those assumptions without seeing the route.

Questions to ask about the option period

Ask how long the developer needs to investigate and what you are paid while the land is reserved. Find out whether the option can be extended, what happens if the utility or local review does not work out and when unused areas are released.

Before agreeing to a lease, ask for the payment start date, increases, access terms and removal responsibilities. A connection proposal does not determine fair terms for your property. Compare the complete rights and obligations, not just the annual rent number.

What to send for an initial review

Provide contact details and a property location. Include the county and municipality if known. A parcel number, approximate acreage, existing utility and current use are helpful additional details.

Tell us whether only part of the property is available and what you want to keep using. You can ask about a lease or sale without choosing one now. Sunland may follow up for records before any project-specific connection or approval conclusions can be reached.

Questions landowners ask

Can a mainland New York map qualify my Long Island site?

No. Use the resources for the actual local utility and connection.

Is filing an application the same as an approved operating project?

No. The utility describes additional review, installation, inspection, testing and signoff steps.

Do I need to research town rules before sending the form?

No. Start with the location and records you have. Current rules and restrictions need checking before a project commitment.

Sources & further reading

Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.