Washington County, Illinois

Battery storage land in Washington County, Illinois

Look beyond the battery footprint to the conditions, land rights and farm use that come with a proposal.

Could my land work?

Washington County has a named battery permit decision and a storage ordinance adopted in July 2026. Neither makes every parcel suitable. Start with a drawing of your land, the applicable approval route and the agreement you are being asked to sign. Then check access, drainage, payment and removal responsibilities together.

What the Gatehouse record actually shows

The June 9, 2026 County Board minutes record an 8–6 vote approving Gatehouse Energy Storage’s special-use permit, Ordinance 2026-130, with conditions. That decision concerns a particular application; it does not establish that the project is operating or that nearby land is being sought.

If a developer refers to that project, ask for the actual permit, conditions and current drawing. Have the team identify what the decision allows, what remains to be completed and which version of the plan it covers.

For a proposal on your land, request its own application reference. Compare the applicant with the company that would sign your option or lease and pay you. A familiar project name is not enough to identify who owes you the obligations.

Keep a dated copy of each decision and drawing supplied. If the proposal changes, ask what changed and which records now support it. Do not rely only on an account of a hearing.

Reference: Washington County: June 9, 2026 minutes, Gatehouse permit vote · Washington County: zoning resources and Gatehouse application

Model landscape illustration of battery enclosures, an electrical substation and a proposed site layout.

Use the right rules for your site

The county-linked July 14, 2026 ordinance applies outside municipal zoning jurisdiction and treats storage integrated with commercial solar or wind under the applicable solar or wind ordinances. Establish the route for the actual parcel and design.

Ask whether the proposal is storage alone, batteries with a new solar project or an addition to an existing facility. Show existing equipment and agreements on the drawing. Have the reviewing office confirm how the proposed use will be considered.

The July text distinguishes a special-use permit from the later building permit and related agreements. Ask the team to explain the remaining steps rather than treating one approval as the whole construction process.

The June Gatehouse vote predates the July ordinance. Have the team establish which approval terms and later requirements govern that project or a changed proposal; do not simply substitute today’s general text for the actual permit conditions.

Reference: Washington County: adopted July 14, 2026 storage ordinance · Washington County: June 9, 2026 minutes, Gatehouse permit vote

Protect the drainage and access you depend on

The July ordinance addresses farmland drainage plans, damage repair and agricultural loss. Ask for the plan for your land and compare it with the arrangements you already use.

Mark tiles, ditches, culverts and wet spots you know about. Explain where water arrives from adjoining land and where it leaves your property. If a route is uncertain, say so; the project team needs to investigate it.

Discuss construction traffic as well as the permanent entrance. Can you still reach fields and buildings during planting or harvest? Where would deliveries wait, and would temporary fencing block a tenant’s route?

Ask how an incident is reported, who investigates it and who pays for repair. Keep records of the existing condition before authorized work begins. Compare those practical arrangements with the private agreement.

Do not let a broad description of the battery area hide other rights. Show the access road, electrical route and temporary work space separately from the land you intend to keep using.

Reference: Washington County: adopted July 14, 2026 storage ordinance

Part of the proposalQuestion for the owner
Permanent equipmentWhich land stays reserved?
Construction accessCan farm and tenant traffic continue?
Drainage workWho investigates and repairs damage?
Temporary work spaceWhen and how is it returned?

Want to ask about your land?

Send the location and what you know. You don’t need a project plan.

Tell us about your land

Understand a setback waiver before signing it

The July ordinance provides for written setback waivers affecting nonparticipating property, with recording and continuing effect on the land. A waiver deserves review as its own document.

Ask for a drawing showing exactly what the waiver changes and which part of your property is affected. Is the request attached to a defined layout? What happens if equipment moves or the design changes?

Have your adviser explain how the wording affects future use or a sale. Compare any payment with the rights requested. Permission for a setback change should not be confused with permission for entry, a road or an electrical easement.

You can ask Sunland about your property without signing a waiver or authorizing work. If you have already received one, explain what you have been asked to do and whether there is a deadline.

Reference: Washington County: adopted July 14, 2026 storage ordinance

Review removal funding alongside the lease

The July ordinance requires a decommissioning plan and financial assurance. Ask for the actual documents and have the beneficiary, amount, updates and use of the security explained.

Check the private removal obligations as well. What equipment, foundations, roads and cables would be removed? What condition would the land be returned to, and how would completion be checked?

Find out who remains responsible if the project changes hands. Keep payment records and current operating contacts with the approvals. A new company name should prompt a clear explanation of the handover.

If the project stops, you should know whom to contact and what records support the next step. Have your adviser compare the permit, removal documents and land agreement rather than assuming they all provide the same rights.

Reference: Washington County: adopted July 14, 2026 storage ordinance

Tell us about the land and your priorities

Start with your name, email and phone number, then the location. Add the current use and whether you would consider a lease, sale or only part of the property. Acreage and other details can follow.

Mention a tenant, drainage arrangement, existing option or offer you have received. Tell us which uses you want to preserve. You do not need a completed site plan to inquire.

Sunland can begin with the information you know. Further review must establish the parcel’s restrictions, connection, approvals and commercial fit before there is a deal to consider.

Questions landowners ask

Does the Gatehouse approval qualify my land?

No. The minutes concern a particular application. Your property needs its own connection, land-use and commercial review.

Is a special-use permit the same as a building permit?

No. The county’s July 2026 text treats these as separate steps. Ask what remains for the actual project.

Should I review a setback waiver separately from a lease?

Yes. Ask what it changes, what drawing it covers and how it affects future use or a sale.

Can I inquire before I have a site plan?

Yes. Start with contact details, the location and what you know about the land.

Sources & further reading

Sources checked 2026-10-04. Local rules and program details can change. Check the requirements for the actual project.