What has actually happened
The Illinois Power Agency reports that the September 1, 2026 results supported 600 MW of new storage: 520 MW in MISO territory and 80 MW in PJM territory. The initial target was 1,038 MW. The awards support development; they do not describe 600 MW already operating.
A statewide shortfall is not a list of vacant parcels being sought. If someone mentions it when approaching you, ask them to connect the announcement to their actual project: its name, proposed location, electrical arrangement and next decision.
Reference: Illinois Power Agency: September 2026 storage procurement results

Where the selected projects are listed
The official September 1 results identify five selected projects. The locations below are those published in the procurement record; they do not establish the municipal boundary, local permit status or a request for neighboring land.
If a developer refers to one of these awards, compare its company and project name with the record. Ask for the actual property drawing and approvals. A nearby award does not tell you whether a separate parcel can connect or what a landowner would be paid.
Reference: IPA procurement administrator: September 1, 2026 selected projects
| Selected project | Published location | Capacity |
|---|---|---|
| Gatehouse Energy Storage LLC | Du Bois | 185 MW |
| KCE IL 1, LLC | Flora | 100 MW |
| KCE IL 2, LLC | Herrick | 100 MW |
| McDuff Battery Storage, LLC | Casey | 135 MW |
| Lincoln Reserve Energy, LLC | Calumet City | 80 MW |
Different records can show different project ratings
The September results list Lincoln Reserve Energy’s selected project at 80 MW. A May 14, 2026 PJM report naming Lincoln Reserve Energy describes request AF2-441, Burnham 138kV, with 200 MW of output, 800 MWh of storage and 80 MW recognized as capacity.
Those figures describe different fields in dated records. Do not add them together, use the award rating to calculate the land needed, or assume the study drawing is the design now offered to you. Ask the company to identify which request and current equipment layout its proposal concerns.
Request the current project name, electrical reference and drawing together. If the offer, award and study use different names or ratings, have the team explain the relationship and any changes. The same company name appearing in two records is not enough to settle the current footprint, approval status or terms.
Ask which number matters to each commitment in your agreement. Would a change to the equipment, operating duration or connection alter the land reserved, rent or construction access? Discuss who must approve those changes before signing an option that leaves the eventual layout open.
Reference: IPA procurement administrator: September 1, 2026 selected projects · PJM: May 14, 2026 Burnham AF2-441 final system impact study, Retool 2
Want to ask about your land?
Send the location and what you know. You don’t need a project plan.
Tell us about your landAsk which part of Illinois and which connection
The split between MISO and PJM matters when discussing a larger project. Ask the developer to identify the grid operator and utility for the proposed connection, rather than relying on the county name or the nearest visible power line.
The Summer 2026 procurement required a physical connection to the applicable grid operator’s transmission system. Distribution-connected storage was not eligible for that event. If your proposal uses a local distribution connection, ask which different commercial route the developer plans to use.
Write down the proposed connection point and any project reference already assigned. Ask whether the site has been screened, entered a study process or received a completed study. Those are different stages. If the developer is still comparing sites, find out how long your property would be held while the comparison continues.
Reference: IPA procurement administrator: Summer 2026 rules, FAQs 11, 72 and 73
Separate the project contract from your land agreement
A developer’s storage contract and your option, lease or purchase agreement answer different questions. A project revenue award does not tell you what you receive, when your payments start or which land rights are requested.
Ask whether a future procurement award is a condition for moving ahead. If it is, identify the expected event, the work to be done beforehand and what happens if the project is not selected. Your documents should explain the payment and release terms during that uncertainty.
The administrator’s September 9 FAQ says there will be no contingency procurement for the Summer 2026 event. It identifies further procurements in 2027 and 2028, with future eligibility still to be developed. Ask for the rules of the event actually being proposed rather than assuming the completed event’s rules will carry over.
Reference: IPA procurement administrator: Summer 2026 rules, FAQs 11, 72 and 73
| Ask about | What you want explained |
|---|---|
| Project revenue | Awarded contract or future bid? |
| Option payment | What is paid while land is reserved? |
| Operating rent | When does it begin, and for what area? |
| Release | What ends the reservation if the bid fails? |
If an offer depends on the next procurement
The IPA’s September 23 feedback request asks about 2027 timing, the MISO/PJM split, project readiness and whether to include hybrid or co-located storage. These are design questions, not final rules for a new bid.
Ask the company which procurement it expects to enter and what has to happen first. Does it have a connection study, a proposed layout or only an initial site screen? Request a short schedule that identifies completed work and the next decision.
Compare that schedule with your option. What would you receive while the company waits? When could it extend the reservation, at what cost and with whose consent? Ask what ends the hold if the final rules do not fit the project.
Discuss what changes would need a new drawing or agreement. A proposal made before final rules may change its equipment, connection or shared use with solar. Identify the land you can offer now and the uses you need to retain so the company can address them before requesting more rights.
Reference: Illinois Power Agency: September 23, 2026 feedback request for future utility-scale procurements
After an award, ask what has actually been completed
The IPA’s September post-award timeline describes contract and product-order execution, performance assurance and later operating obligations. It is a reference summary; the underlying contract and RFP rules govern.
If a company cites a selected project, ask whether the contract was executed and what remains before construction. A posted deadline does not show that a particular company met it. Request a current update tied to the project named in your offer.
Section 2.3 of the 2026 contract sets a December 31, 2029 operating deadline with a conditional extension to December 31, 2030. Section 7 addresses assurance held by the utility buyer.
Have your adviser compare those project obligations with your land agreement. A project extension does not explain what happens to your option end date or rent start. If the company cannot proceed, how would it release recorded rights and repair investigation damage?
If someone says the project is “bonded,” ask which document they mean and who it protects. Review the security for rent, property damage and removal separately. Find out who can claim each protection, when it expires and what happens after a project transfer.
Reference: Illinois Power Agency: September 2026 post-award timeline, reference summary · IPA procurement administrator: final June 29, 2026 Indexed Storage Credit Agreement
Storage for All is still being developed
The September 30 Storage for All request concerns batteries co-located with Illinois Solar for All projects. It says public availability will be no earlier than 2028. The draft procurement plan is due June 1, 2027, followed by further review.
That schedule is not an incentive application window for a vacant parcel. If an offer refers to Storage for All, ask which existing or planned solar project it concerns and why the company expects the battery proposal to fit. Keep the program discussion separate from the land payment being offered.
For a battery addition, bring out the existing solar agreement and approved drawing. What space and access does that agreement already cover? Would batteries change your remaining use of the property, the equipment owner or the removal arrangements? Ask for the changes to be shown before signing an amendment.
If the proposal depends on future funding, ask who pays for work carried out before a decision and what happens if that funding does not arrive. A developing program should not leave the property reserved without understandable payment and release terms.
Reference: Illinois Power Agency: September 30, 2026 Storage for All development request, timing on PDF page 3
Do not reserve more than you understand
Ask for the equipment area, entrance, electrical route and temporary construction space to be shown separately. Mark areas you want to keep farming, leasing or using for another building. Explain any shared access or existing tenant rights early.
Find out whether the developer can change the footprint during studies and how you would agree to that change. If only part of an option area is eventually used, ask when the rest is released. A project can change size without your retained-use priorities changing.
Start with the property, not a bid application
To ask Sunland about your land, send the location and contact details. Add the current use, approximate available area and any proposal already received. You do not need to enter a state procurement yourself to start that conversation.
If you have a developer’s letter, identify the program or project it names. We can begin with that information. Further review still needs to establish the connection, approvals, costs and commercial fit; a state award elsewhere does not qualify your parcel.
Questions landowners ask
Does Illinois pay a landowner through the storage procurement?
The project procurement is separate from your private land agreement. Ask the developer to explain your own payments and obligations.
Does the 600 MW award mean those batteries are operating?
No. The announcement describes contracts supporting development.
Was distribution-connected storage eligible for this procurement?
No. The Summer 2026 event required a physical transmission-system connection. This does not establish the rules for every storage opportunity or future procurement.
Should I wait until a developer wins a future bid?
You can inquire now. Before reserving land, understand the option payments, time limits and release terms if the bid fails.
Sources & further reading
Sources checked 2026-10-06. Local rules and program details can change. Check the requirements for the actual project.
- Illinois Power Agency: September 2026 storage procurement results
- Illinois Power Agency: storage procurements and program development
- IPA procurement administrator: September 1, 2026 selected projects
- PJM: May 14, 2026 Burnham AF2-441 final system impact study, Retool 2
- IPA procurement administrator: Summer 2026 rules, FAQs 11, 72 and 73
- Illinois Power Agency: September 23, 2026 feedback request for future utility-scale procurements
- Illinois Power Agency: September 2026 post-award timeline, reference summary
- IPA procurement administrator: final June 29, 2026 Indexed Storage Credit Agreement
- Illinois Power Agency: September 30, 2026 Storage for All development request, timing on PDF page 3